Construction Updates

 

ESFM-C092(75)--55-92 Vine Ave Pavement Overlay

Location: Vine Ave south of Hwy 22 to 160th Street (4.0 miles)

Letting Date: April 21, 2009

Final Cost : $1,474,229

Contractor: Concrete Foundations Inc., New Hampton, IA

Completion Date: September 17, 2009

Comments: This project was partially funded with funds from the "American Recovery and Reinvestment Act of 2009."

 

FM-C092(67)--55-92 McCreedy Culvert on Vine Ave

Location: On Vine Ave 5 miles north of Ainsworth

Letting Date: April 21, 2009

Contract Amount : $234,917

Contractor: Winfield Contractors, Wapello, IA

Start Date: Week of August 17, 2009

Comments: This is a single box RCB Culvert Replacement

Detour Routes: Road is closed to through traffic. Contractor will maintain access to local landowners

 

BRS-C092(59)--60-92 Keota Triple Box Culvert

Location: 3 miles northeast of Keota on G26

Letting Date: March 17, 2009

Contract Amount : $301,218

Contractor: Helmkamp Construction of Iowa, Inc., Ankeny, IA

Start Date: August 13, 2009

Comments: This is a triple box culvert replacing a deteriorating bridge on G26.

Detour Routes: Road will be closed to through traffic. Contractor will maintain access to local landowners

 

2009 Local Culverts

Location: Vine Ave between 135th Street and 150th Street

Letting Date: March 31, 2009

Final Cost : $72,599

Contractor: McCulley Culvert, Barnes City, IA

Completion Date: May 12, 2009

Comments: Includes a 8' x 6' concrete culvert extension on Vine Ave.

 

L-L-364 Wellston Crossing

Location: 275th and Fir Avenue

Completion Date: June 25, 2008

Project Cost: After several years of litigation, the IC&E Railroad and Washington County reached a settlement of $90,000 to build the at-grade crossing. The railroad placed the actual crossing at their expense.

Contractor: Washington County

Comments: This is an at-grade railroad crossing to replace the railroad bridge that was vandalized and burnt down.

 

L-K-111 230th Street Bridge

Location: 2.0 mile west of Hwy 1/92 on 230th Street

Completion Date: November 14, 2008

Project Cost: $73,901.50 + County expenses for RR flat cars and day labor

Contractor: Iowa Bridge & Culvert

Comments: This bridge utilizes railroad flat cars similar to the bridge built near Richmond in 2007.

 

FM-C092(65)--55-92 Underwood Ave Bridge

Location: On Underwood Ave approximately 0.75 miles south of Hwy 92

Completion Date: May 8, 2009

Project Cost: $426,587

Contractor: Schmidt Construction Company, Inc., Winfield, IA

Estimated Start Date: November 2008.

Comments: This is a 126' by 34' pretensioned prestressed concrete beam bridge over the south fork of Long Creek.

 

FM-C092(66)--55-92 Vine Ave Paving Overlay

Location: Vine Ave north of Hwy 22 to Johnson County line

Completion Date: September 5, 2008

Project Cost: $726,235

Contractor: Manatts, Inc. of Brooklyn, IA

 

L-L-032 Grading on W21

Location: First 4.5 miles south of G38 on Elm Ave, 275th St, and Dogwood Ave

Completion Date: May 1, 2009

Project Cost: $1,089,236

Contractor: Cole Construction Co, Inc., Keosauqua, IA

Comments: This is a 4.5 mile grading project with approximately 20 culverts to be completed. This is the second phase of reconstruction with eventual paving of the road to provide a paved crossing over the Skunk River between Brighton and Richland.

 