Construction Updates

 

BROS-CO92(69)--8J-92 Hickory Ave Bridge Replacement

Location: On Hickory Ave over Smith Creek approximately 2 mi. east of Wellman, IA

Letting Date: July 20, 2010

Contract Amount: $460,865.61

Contractor: Peterson Contractors Inc. of Reinbeck, IA

Comments:

Detour Routes:

 

FM-C092(70)--55-92 Twin Box Culvert on W38

Location: On W38 between 170th & 180th St

Letting Date: June 20, 2010

Contract Amount: $161,727

Contractor: Iowa Bridge & Culvert, Washington, IA

Comments: Beginning on Monday, August 9th, 2010 W38 will be closed to thru-traffic between 170th & 180th Streets, approximately 4 miles south of Wellman for this project. Iowa Bridge & Culvert will remove the 25' x 22' concrete slab bridge and replace it with a twin 10' x 8' x 79' reinforced concrete box culvert. Construction should be completed in approximately 3 months.

Detour Routes: Traffic should detour onto County Highway G20 to State Highway 1 then back on County Highway G26.

 

BRS-C092(42)--55-92 Railroad Bridge on G38

Location: Over Crooked Creek east of Washington in Section 24-75-8

Letting Date: May 18, 2010

Contract Amount: $737,437

Contractor: Iowa Bridge & Culvert, Washington, IA

Comments: Iowa Bridge and Culvert will remove the existing deteriorating bridge and replace it with a wider bridge that will improve the existing low clearance under the rail road bridge.  Construction should be completed in 6 months depending on weather delays.

Detour Routes: Traffic will be detoured on to county road W-38 and Highway 92 during construction.

 

ESFM-C092(75)--55-92 Vine Ave Pavement Overlay

Location: Vine Ave south of Hwy 22 to 160th Street (4.0 miles)

Completion Date: September 17, 2009

Final Cost : $1,474,229

Contractor: Concrete Foundations Inc., New Hampton, IA

Comments: This project was partially funded with funds from the "American Recovery and Reinvestment Act of 2009."

 

FM-C092(67)--55-92 McCreedy Culvert on Vine Ave

Location: On Vine Ave 5 miles north of Ainsworth

Completion Date: April 26, 2010

Final Cost: $227,630

Contractor: Winfield Contractors, Wapello, IA

Comments: This is a single box RCB Culvert Replacement

 

BRS-C092(59)--60-92 Keota Triple Box Culvert

Location: 3 miles northeast of Keota on G26

Completion Date: April 16, 2010

Final Cost: $282,131

Contractor: Helmkamp Construction of Iowa, Inc., Ankeny, IA

Comments: This is a triple box culvert replacing a deteriorating bridge on G26.

 

2009 Local Culverts

Location: Vine Ave between 135th Street and 150th Street

Letting Date: March 31, 2009

Final Cost : $72,599

Contractor: McCulley Culvert, Barnes City, IA

Completion Date: May 12, 2009

Comments: Includes a 8' x 6' concrete culvert extension on Vine Ave.

 

L-L-364 Wellston Crossing

Location: 275th and Fir Avenue

Completion Date: June 25, 2008

Project Cost: After several years of litigation, the IC&E Railroad and Washington County reached a settlement of $90,000 to build the at-grade crossing. The railroad placed the actual crossing at their expense.

Contractor: Washington County

Comments: This is an at-grade railroad crossing to replace the railroad bridge that was vandalized and burnt down.

 

L-K-111 230th Street Bridge

Location: 2.0 mile west of Hwy 1/92 on 230th Street

Completion Date: November 14, 2008

Project Cost: $73,901.50 + County expenses for RR flat cars and day labor

Contractor: Iowa Bridge & Culvert

Comments: This bridge utilizes railroad flat cars similar to the bridge built near Richmond in 2007.

 

FM-C092(65)--55-92 Underwood Ave Bridge

Location: On Underwood Ave approximately 0.75 miles south of Hwy 92

Completion Date: May 8, 2009

Project Cost: $426,587

Contractor: Schmidt Construction Company, Inc., Winfield, IA

Estimated Start Date: November 2008.

Comments: This is a 126' by 34' pretensioned prestressed concrete beam bridge over the south fork of Long Creek.

 

FM-C092(66)--55-92 Vine Ave Paving Overlay

Location: Vine Ave north of Hwy 22 to Johnson County line

Completion Date: September 5, 2008

Project Cost: $726,235

Contractor: Manatts, Inc. of Brooklyn, IA

 

L-L-032 Grading on W21

Location: First 4.5 miles south of G38 on Elm Ave, 275th St, and Dogwood Ave

Completion Date: May 1, 2009

Project Cost: $1,089,236

Contractor: Cole Construction Co, Inc., Keosauqua, IA

Comments: This is a 4.5 mile grading project with approximately 20 culverts to be completed. This is the second phase of reconstruction with eventual paving of the road to provide a paved crossing over the Skunk River between Brighton and Richland.

 


«BACK | Site Index | Common Questions